Risk analysis of material management that causes cost and time deviations in high-story building projects
Keywords:
AHP (analytical hierarchy process), material management, mitigation actions, risk analysisAbstract
Construction Work Project for Maternal and Child Health Services Building of RSUP Prof. Dr. IGN. Ngoerah Denpasar Bali is a multi-storey building project that has an area of 18,226 m2 which is targeted for completion on November 27, 2023. To get the time to complete the work on time, it is necessary to anticipate various risks that occur, one of which is the risk of material management during project construction. From the research to be carried out, material management risks that affect time delays and cost deviations in the project will be identified using the AHP (Analytic Hierarchy Process) method. This study will identify the level of risk or risk index that most dominantly affects time delays and cost deviations. The most dominant material management risks that have been identified will then be mitigated to reduce the identified dominant risks. Based on the results of the analysis, 30 risk variables were identified for cost performance and 34 risk variables were identified for time performance.
Downloads
References
Akintoye, A. S., & MacLeod, M. J. (1997). Risk analysis and management in construction. International journal of project management, 15(1), 31-38. https://doi.org/10.1016/S0263-7863(96)00035-X
Aminbakhsh, S., Gunduz, M., & Sonmez, R. (2013). Safety risk assessment using analytic hierarchy process (AHP) during planning and budgeting of construction projects. Journal of safety research, 46, 99-105. https://doi.org/10.1016/j.jsr.2013.05.003
Andani, S. (2011). Analisa resiko manajemen material dominan yang berpengaruh terhadap kinerja waktu pelaksanaan proyek gedung bertingkat BUMN. Tugas Akhir Departemen Teknik Sipil, Fakultas Teknik, Universitas Indonesia, Depok.
Ardi, A. W. (2016). Analisis risiko manajemen material dan pengaruh tindakan koreksi pada proyek gedung bertingkat.
Chan, F. T. S., Ip, R. W. L., & Lau, H. (2001). Integration of expert system with analytic hierarchy process for the design of material handling equipment selection system. Journal of Materials Processing Technology, 116(2-3), 137-145. https://doi.org/10.1016/S0924-0136(01)01038-X
Dey, P. K. (2010). Managing project risk using combined analytic hierarchy process and risk map. Applied Soft Computing, 10(4), 990-1000. https://doi.org/10.1016/j.asoc.2010.03.010
Eskander, R. F. A. (2018). Risk assessment influencing factors for Arabian construction projects using analytic hierarchy process. Alexandria engineering journal, 57(4), 4207-4218. https://doi.org/10.1016/j.aej.2018.10.018
Hwang, B. G., Shan, M., & Supa’at, N. N. B. (2017). Green commercial building projects in Singapore: Critical risk factors and mitigation measures. Sustainable cities and Society, 30, 237-247. https://doi.org/10.1016/j.scs.2017.01.020
Islam, R., Nazifa, T. H., Mohammed, S. F., Zishan, M. A., Yusof, Z. M., & Mong, S. G. (2021). Impacts of design deficiencies on maintenance cost of high-rise residential buildings and mitigation measures. Journal of Building Engineering, 39, 102215. https://doi.org/10.1016/j.jobe.2021.102215
Labombang, M. (2011). Manajemen risiko dalam proyek konstruksi. SMARTek, 9(1).
Mahdi, I. M., & Alreshaid, K. (2005). Decision support system for selecting the proper project delivery method using analytical hierarchy process (AHP). International journal of project management, 23(7), 564-572. https://doi.org/10.1016/j.ijproman.2005.05.007
Mufty, F. (2018). Mitigasi Risiko Pada Penjadwalan Proyek Pekerjaan Network Improvement Quality Equipment (NIQE) FIBER OPTIC (Studi Kasus PT. Indo Com Nusantara).
Mukhlis, M., Natalia, M., Lusyana, L., Satwarnirat, S., & Yuma, A. R. (2019). Analisa Faktor-Faktor Mempengaruhi Penyimpangan Biaya Material Terhadap Kinerja Biaya Akhir Proyek Gedung di Kota Padang. Jurnal Ilmiah Rekayasa Sipil, 16(1), 39-46.
Öztaş, A., & Ökmen, Ö. (2005). Judgmental risk analysis process development in construction projects. Building and environment, 40(9), 1244-1254. https://doi.org/10.1016/j.buildenv.2004.10.013
Santiana, I., Wibawa, I., Yasa, I., Suasira, I. W., & Sutapa, I. K. (2022). Factors Caused for Delays and Alternatives in The Denpasar Living World Mall Building Project. International research journal of engineering, IT & scientific research, 8(6), 299-305.
Santoso, B., & Proyek, M. (2009). Konsep dan Implementasi. Yogyakarta: Graha Ilmu.
Siswanto, A. B., & Salim, M. A. (2019). Manajemen Proyek. CV. Pilar Nusantara.
Suasira, I. W., Intara, I. W., Sutapa, I. K., Santiana, I., Wibawa, I., & Yasa, I. (2022). Structure Analysis of Building Functions Transition on The Earthquake Area five Reviewed from Costs and Time Schedule. International research journal of engineering, IT & scientific research, 8(1), 7-16.
Subramanian, N., & Ramanathan, R. (2012). A review of applications of Analytic Hierarchy Process in operations management. International Journal of Production Economics, 138(2), 215-241. https://doi.org/10.1016/j.ijpe.2012.03.036
Sugiharto, R. (2020). Analisis faktor-faktor dominan manajemen risiko terhadap kinerja keuangan proyek tahap konstruksi. Jurnal Teknik Sipil Dan Lingkungan Universitas Nusa Putra (J-Teslink), 1, 1-11.
Sugiyono, P. D. (2020). Metode Penelitian Kualitatif Untuk Penelitian Yang Bersifat: Eksploiratif, Enterpretif Dan Konstruktif. Edited By Y. Suryandari. Bandung: ALFABETA.
Trisnayanti, N. M. A., Santiana, I., & Triadi, I. (2023). Analisis Risiko Terhadap Manajemen Material yang Menyebabkan Penyimpangan Biaya dan Waktu pada Proyek Gedung Bertingkat (Studi Kasus: Pekerjaan Konstruksi Gedung Pelayanan Kesehatan Ibu dan Anak RSUP Prof. Dr. IGN. Ngoerah Denpasar Bali) (Doctoral dissertation, Politeknik Negeri Bali).
Widiarso, A. (2010). Pengaruh Manajemen Material Terhadap Produktivitas Kerja Proyek Konstruksi Gedung Bertingkat Pada Pekerjaan Struktur (Studi Kasus: Proyek-X). Fakultas Teknik Universitas Indonesia, Depok.
Published
How to Cite
Issue
Section
Copyright (c) 2023 International research journal of engineering, IT & scientific research

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
Articles published in the International Research Journal of Engineering, IT & Scientific research (IRJEIS) are available under Creative Commons Attribution Non-Commercial No Derivatives Licence (CC BY-NC-ND 4.0). Authors retain copyright in their work and grant IRJEIS right of first publication under CC BY-NC-ND 4.0. Users have the right to read, download, copy, distribute, print, search, or link to the full texts of articles in this journal, and to use them for any other lawful purpose.
Articles published in IRJEIS can be copied, communicated and shared in their published form for non-commercial purposes provided full attribution is given to the author and the journal. Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgment of its initial publication in this journal.
This copyright notice applies to articles published in IRJEIS volumes 6 onwards. Please read about the copyright notices for previous volumes under Journal History.