Analysis productivity and its impact on time and cost of implementation of the private residence project structure work
Keywords:
Cost, Crash Duration, Human Resources, Project Optimization, TimeAbstract
The construction project of Mrs. Tiya & Mr. Tom's Private Residence in Kemenuh-Gianyar is a 3-story villa development chosen as a case study due to discrepancies between the consultant's plans and the actual field conditions. This necessitated a method to optimize work completion. One proposed solution for accelerating the project was to add more workers. Based on the initial plan, the project required 104 days (3 months and 2 weeks) for completion, with a total structural work cost of Rp. 703,803,162.24. After analysis with the alternative of adding more workers, the project completion duration could return to the schedule of 90 days (3 months) or be accelerated by 12 days (2 weeks), with a total cost of Rp. 671,298,258.93. This concludes that adding more workers is an effective method to increase time efficiency by 14.29% and decrease costs by 4.6%, or the equivalent of Rp. 32,504,903.31.
Downloads
References
Alji. M. (2024). Analisis Percepatan Proyek Rumah melalui Penambahan Tenaga Kerja.
Apriliani, R. A., & Cahyono, B. N. (2023). Analisis Percepatan Proyek Dengan Menggunakan Metode Crashing. Narotama Jurnal Teknik Sipil, 7(1), 43-52.
Asroni, A. (2010). Kolom Fondasi dan Balok T Beton Bertulang. Yogyakarta: Graha Ilmu.
Herlina, N. (2017). Permasalahan lingkungan hidup dan penegakan hukum lingkungan di Indonesia. Jurnal Ilmiah Galuh Justisi, 3(2), 162-176.
Huemann, M., Keegan, A., & Turner, J. R. (2007). Human resource management in the project-oriented company: A review. International journal of project management, 25(3), 315-323. https://doi.org/10.1016/j.ijproman.2006.10.001
Jusmidah, J. (2016). Analisis Produktivitas Tenaga Kerja Pada Proyek Pekerjaan Jembatan Amassangan. PENA TEKNIK: Jurnal Ilmiah Ilmu-Ilmu Teknik, 1(1), 47-54.
Meivian, A. (2021). Perancangan Struktur Bawah Gedung Operasional Pt. Marga Mandalasakti Dengan Bored Pile. Jurnal Teknik Sipil Universitas Serang Raya, 1(1), 18-40.
Pohan, A. H., Indriasari, I., & Bangun, S. (2022). Metode pelaksanaan pekerjaan konstruksi struktur bawah pada perkantoran Danayasa Tower. Jurnal Teknik, 11(1).
Rabbani, M., Bajestani, M. A., & Khoshkhou, G. B. (2010). A multi-objective particle swarm optimization for project selection problem. Expert systems with applications, 37(1), 315-321. https://doi.org/10.1016/j.eswa.2009.05.056
Rompas, L. M. (2022). Analisis Proporsi Sumber Daya Pada Proyek Konstruksi (Studi Kasus Kota Manado). Tekno, 20(82), 1189-1194.
Saputra, H. (2019). Identifikasi Faktor-Faktor Yang Berpengaruh Terhadap Produktivitas Tenaga Kerja (Studi Kasus: Proyek Pembangunan Perumahan Mutiara Garuda, Panam Pekanbaru) (Doctoral dissertation, Universitas Islam Riau).
Siregar, H. K. A., Harahap, S., & Puspita, N. R. (2022). Analisa Perbandingan Nilai Harga Satuan Pekerjaan (AHSP) Dengan Nilai Harga Standar Nasional Indonesia (Sni) Pada Pekerjaan Pembangunan Gedung/Ruang Baru Puskesmas Padangmatinggikota Padangsidimpuan. Statika, 5(1), 60-70.
Thapa, D., Mishra, S., Velaga, N. R., & Patil, G. R. (2024). Advancing proactive crash prediction: A discretized duration approach for predicting crashes and severity. Accident Analysis & Prevention, 195, 107407. https://doi.org/10.1016/j.aap.2023.107407
Ujung, G. K. N. (2024). Perhitungan Pengendalian Bahan dan Tenaga Kerja Pekerjaan Struktur Proyek Pembangunan Villa 2 Bedroom Echo Beach Canggu (Doctoral dissertation, Politeknik Negeri Bali).
Wibawa, I. G. S., Santiana, I. M. A., Suasira, I. W., Sudiasa, I. W., & Sumardika, A. A. N. R. (2023). Risk analysis of material management that causes cost and time deviations in high-story building projects. International Research Journal of Engineering, IT and Scientific Research, 9(6), 231–239. https://doi.org/10.21744/irjeis.v9n6.2378
Published
How to Cite
Issue
Section
Copyright (c) 2025 International research journal of engineering, IT and scientific research

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
Articles published in the International Research Journal of Engineering, IT & Scientific research (IRJEIS) are available under Creative Commons Attribution Non-Commercial No Derivatives Licence (CC BY-NC-ND 4.0). Authors retain copyright in their work and grant IRJEIS right of first publication under CC BY-NC-ND 4.0. Users have the right to read, download, copy, distribute, print, search, or link to the full texts of articles in this journal, and to use them for any other lawful purpose.
Articles published in IRJEIS can be copied, communicated and shared in their published form for non-commercial purposes provided full attribution is given to the author and the journal. Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgment of its initial publication in this journal.
This copyright notice applies to articles published in IRJEIS volumes 6 onwards. Please read about the copyright notices for previous volumes under Journal History.