Determinants of variation orders and their impact on cost overrun in coastal construction projects

A case study in Bali, Indonesia

https://doi.org/10.21744/irjeis.v12n2.2600

Authors

  • I Made Anom Santiana Politeknik Negeri Bali, Badung, Indonesia
  • I Gede Sastra Wibawa Politeknik Negeri Bali, Badung, Indonesia
  • I Wayan Wiraga Politeknik Negeri Bali, Badung, Indonesia
  • I Wayan Sujahtra Politeknik Negeri Bali, Badung, Indonesia
  • I Made Budiadi Politeknik Negeri Bali, Badung, Indonesia
  • M. Yusuf Politeknik Negeri Bali, Badung, Indonesia

Keywords:

coastal construction, construction project management, cost overrun, environmental uncertainty, scope changes, variation orders

Abstract

Cost overruns remain a persistent challenge in construction projects, particularly in environmentally complex settings such as coastal areas. This study aims to analyse the determinants of variation orders and their impact on cost overruns in coastal construction projects, using a case study in Bali, Indonesia. A quantitative approach was adopted, with data collected through structured questionnaires from 30 construction professionals, including project managers, engineers, and quantity surveyors. The data were analysed using multiple linear regression to examine the influence of design, specification, safety, and scope-related factors on cost overruns. The results indicate that variation orders have a significant effect on cost overruns, both simultaneously and partially. Among the examined variables, scope changes were identified as the most dominant factor, followed by design, safety, and specification factors. These findings suggest that instability in project scope, combined with design revisions and operational adjustments, plays a critical role in driving cost escalation. Importantly, this study reveals that variation orders in coastal construction projects are not solely driven by internal project factors but are also strongly influenced by environmental uncertainty, such as tidal conditions, shoreline dynamics, and regulatory requirements. 

Downloads

Download data is not yet available.

References

Al-Btoush, M., Bassam, A., Khraisat, S., Al-Btoosh, J. F. A. A., Jasim, N. A., Rawashdeh, T. T., & Varouqaa, I. F. (2024). Building information modeling capability in mitigating change orders and cost overrun. Journal of Advanced Sciences and Engineering Technologies, 7(1), 63-80.

Alonso-Iglesias, G., Ortega-Fernández, F., Rodríguez-Montequín, V., Skitmore, M., & Ogunmakinde, O. E. (2023). The Relationship between Cost Overruns and Modifications for Construction Projects: Spanish Public Works and Their Legal Framework. Buildings, 13(10), 2626.

Banihashemi, S., Hosseini, M. R., Golizadeh, H., & Sankaran, S. (2017). Critical success factors (CSFs) for integration of sustainability into construction project management practices in developing countries. International journal of project management, 35(6), 1103-1119. https://doi.org/10.1016/j.ijproman.2017.01.014

Creswell, J. W., & Creswell, J. D. (2017). Research design: Qualitative, quantitative, and mixed methods approaches. Sage publications.

Dong, S., Ahmed, M., & Chatpattananan, V. (2025). Analysis of key factors of cost overrun in construction projects based on structural equation modeling. Sustainability, 17(5), 2119.

Endawati, E., & Susetyo, B. (2023). Evaluation of design change and material availability on cost performance. Journal of Social Research, 2(5), 1691–1707.

Hair, J. F., Black, W. C., Babin, B. J., & Anderson, R. E. (2019). Multivariate data analysis (8th ed.). Cengage Learning.

Hwang, B. G., Zhao, X., & Goh, K. J. (2021). Investigating the impact of change orders on construction cost performance. Journal of Building Engineering, 33, 101856.

Khalafalla, M., Mulay, T., & Bernadin, S. L. (2025). Factors Influencing Change Orders in Horizontal Construction Projects: A Comparative Analysis of Unit Price and Lump Sum Contracts. arXiv preprint arXiv:2507.00281.

Khoshkonesh, A., Mohammadagha, M., & Ebrahimi, N. (2025). Integrated 4D/5D Digital-Twin Framework for Cost Estimation and Probabilistic Schedule Control: A Texas Mid-Rise Case Study. arXiv preprint arXiv:2511.15711.

Mohammad, K. H., Ali, N. S., & Najm, B. M. (2021). Assessment of the cost and time impact of variation orders on construction projects in Sulaimani governorate. Journal of Engineering, 27(2), 106-125.

Ramadhan, J. S., & Waty, M. (2025). Impact of change orders on cost overruns and delays in large-scale construction projects. Engineering, Technology & Applied Science Research, 15(1), 20291-20299.

Santiana, I. M. A., & Yusuf, M. (2020). Design of Arrangement of Working Time to Increase Productivity of the Workers by Using Flat Iron at Garment “A”. Logic: Jurnal Rancang Bangun dan Teknologi, 20(1), 35-39.

Senouci, A., Ismail, A., & Eldin, N. (2016). Time delay and cost overrun in Qatari public construction projects. Procedia Engineering, 164, 368–375.

Shugran, A. A., & Ghazali, F. M. (2025). Understanding the effects of variation orders on construction project success: insights from the Jordanian context. International Journal of Construction Management, 25(5), 519-529.

Sovacool, B. K., Gilbert, A., & Nugent, D. (2014). An international comparative assessment of construction cost overruns for electricity infrastructure. Energy Research & Social Science, 3, 152-160. https://doi.org/10.1016/j.erss.2014.07.016

Suarbawa, I. K. G. J., Yusuf, M., & Sudiajeng, L. (2024). Ergonomic Factors Which Affect the Work Productivity of Clove Flower Harvesters. International Journal on Advanced Science, Engineering and Information Technology, 14(2 SE-Articles), 675–682.

Sudiajeng, L., Tarwaka, T., Sutapa, I. K., Sudana, M., & Yusuf, M. (2023). Ergonomic tetrapod reduces the MSDs risk and productivity of steel-bar assembly for reinforcement concrete beams. International research journal of engineering, IT & scientific research, 9(1), 1-13.

Vecchiato, R. (2012). Environmental uncertainty, foresight and strategic decision making: An integrated study. Technological Forecasting and Social Change, 79(3), 436-447. https://doi.org/10.1016/j.techfore.2011.07.010

Wang, R., Samarasinghe, D. A. S., Skelton, L., & Rotimi, J. O. B. (2022). A study of design change management for infrastructure development projects in New Zealand. Buildings, 12(9), 1486.

Wibawa, I. G. S., Santiana, I. M. A., Suasira, I. W., Sudiasa, I. W., & Sumardika, A. A. N. R. (2023). Risk analysis of material management that causes cost and time deviations in high-story building projects. International Research Journal of Engineering, IT and Scientific Research, 9(6), 231–239. https://doi.org/10.21744/irjeis.v9n6.2378

Wibowo, W. P. (2023). Analysis of contract change order costs in building construction projects. Asian Journal of Engineering Social and Health, 2(12), 1719–1732.

Yusuf, M., Suarbawa, I. K. G. J., & Santiana, I. M. A. (2025). Factors affecting the workload of horticultural farmers in agrotourism areas. Multidisciplinary Science Journal, 7(3), 2025136-2025136.

Yusuf, M., Sudiajeng, L., Suryawan, K. A., & Sudana, I. M. (2022). Redesign of Ergonomic Worktables in Reinforced Concrete Sheet Works Reduce Ergonomic Risk Level. In Proceedings of the 5th International Conference on Applied Science and Technology on Engineering Science iCAST-ES, ScitePress Digital Library (pp. 370-374).

Published

2026-04-02

How to Cite

Santiana, I. M. A., Wibawa, I. G. S., Wiraga, I. W., Sujahtra, I. W., Budiadi, I. M., & Yusuf, M. (2026). Determinants of variation orders and their impact on cost overrun in coastal construction projects: A case study in Bali, Indonesia. International Research Journal of Engineering, IT and Scientific Research, 12(2), 14–24. https://doi.org/10.21744/irjeis.v12n2.2600

Issue

Section

Research Articles