Time–cost trade-off analysis using the precedence diagram method in residential construction projects

A case study in Bali, Indonesia

https://doi.org/10.21744/irjeis.v12n3.2604

Authors

  • I Gede Sastra Wibawa Politeknik Negeri Bali, Badung, Indonesia
  • I Made Anom Santiana Politeknik Negeri Bali, Badung, Indonesia
  • I Wayan Wiraga Politeknik Negeri Bali, Badung, Indonesia
  • I Wayan Arya Politeknik Negeri Bali, Badung, Indonesia
  • Surya Negara Dwipa RS Politeknik Negeri Bali, Badung, Indonesia
  • M. Yusuf Politeknik Negeri Bali, Badung, Indonesia

Keywords:

construction project acceleration, crashing method, precedence diagram method, project scheduling, time–cost trade-off

Abstract

Construction project delays remain a major challenge in the construction industry because they significantly affect project cost, productivity, and overall project performance. Residential construction projects in tourism-oriented regions such as Bali are particularly vulnerable to schedule deviations due to design changes, labor shortages, and coordination problems, which may reduce investment performance and operational readiness. Therefore, effective project acceleration strategies are required to minimize delays while maintaining cost efficiency. This study aims to analyze the time–cost trade-off resulting from project acceleration using the Precedence Diagram Method (PDM) and crashing techniques in the Brand New Modern Villa Berawa Canggu Project, Bali, Indonesia. The research employed a quantitative descriptive approach using primary and secondary project data, including work schedules, labor productivity, overtime wages, and project cost data. PDM analysis was conducted using Microsoft Project to identify critical activities, followed by crashing analysis through overtime work and additional labor allocation. The results indicate that project acceleration successfully reduced the project duration from 413 calendar days to 392 calendar days, resulting in a total time efficiency of 21 days. 

Downloads

Download data is not yet available.

References

Abdelalim, A. M., Salem, M., Salem, M., Al-Adwani, M., & Tantawy, M. (2025). Analyzing Cost Overrun Risks in Construction Projects: A Multi-Stakeholder Perspective Using Fuzzy Group Decision-Making and K-Means Clustering. Buildings, 15(3), 447.

Afrida, W. D., Renjani, M. S., Rahmawati, D., & Radinal. (2025). Comparative analysis of time and cost efficiency in project acceleration strategies: A case study of the construction of a police service building. Global Education Journal, 3(1), 211–217.

Ariany, F. (2017). Analysis of project acceleration by increasing optimum working hours in construction projects. Jurnal Ilmiah Teknik Sipil, 14(2), 120–129.

Bastini, F. J., & Ulandari, A. H. T. (2026). Dominant Factors Causing Construction Project Delays in Indonesia and Their Mitigation Strategies: A Literature Review. Jurnal Teknik Sipil, 1(1), 16-23.

Dewanto, W. P. (2024). Analysis of project time and cost using the crash program method with overtime and additional labor alternatives. CIVED Journal, 11(3), 1057–1068.

Eshtehardian, E., Afshar, A., & Abbasnia, R. (2009). Fuzzy-based MOGA approach to stochastic time–cost trade-off problem. Automation in construction, 18(5), 692-701. https://doi.org/10.1016/j.autcon.2009.02.001

Flyvbjerg, B., Budzier, A., Lee, J. S., Keil, M., Lunn, D., & Bester, D. W. (2022). The empirical reality of IT project cost overruns: Discovering a power-law distribution. Project Management Journal, 53(4), 1–15.

Gong, Y., Yang, K., Seo, J., & Lee, J. G. (2022). Wearable acceleration-based action recognition for long-term and continuous activity analysis in construction site. Journal of Building Engineering, 52, 104448. https://doi.org/10.1016/j.jobe.2022.104448

Gunawan, M. I., Suryana, H., Patra, O., & Nugraha, E. (2025). Analysis of Delay Factors in EPC Power Plant Projects (Case Study: PLTMG Project in Sumbawa). Journal Research of Social Science, Economics & Management, 5(2).

Hartmann, S., & Briskorn, D. (2022). An updated survey of variants and extensions of the resource-constrained project scheduling problem. European Journal of Operational Research, 297(1), 1–14.

Kurniawan, B. N., & Mulyono, N. B. (2024). Minimizing delay in construction project at PT Freeport Indonesia using crashing CPM-PERT approach and Monte Carlo simulation. European Journal of Business Management and Research, 9(5), 61–69.

Lutfi, M. A., Witjaksana, B., & Purnama, J. (2025). Cost and Time Analysis of Project Acceleration using the Crashing Method with Additional Working Hours and Labor. Asian Journal of Social and Humanities, 3(7), 1430-1438.

Naufal, Z. S. (2025). Optimization of time and cost using Precedence Diagram Method (PDM) in construction projects. Journal of Civil Engineering and Planning, 4(2), 130–138.

Nurhidayat, A. A. (2021). Optimization of apartment construction projects using Precedence Diagram Method (PDM). Jurnal Teknik Industri, 10(1), 22–32.

Paradiba, H., & Mirnayani. (2025). The impact of overtime duration variations on labor productivity and labour utilization rate in apartment construction projects. Calamity, 2(2), 118–126.

Poerba, Y., et al. (2022). Analysis of project acceleration using crashing method in building construction projects. Jurnal Teknik ITS, 11(3), 45–53.

Ramadhan, J. S., & Waty, M. (2025). Impact of change orders on cost overruns and delays in large-scale construction projects. Engineering, Technology & Applied Science Research, 15(1), 20291–20299.

Restrepo, A. F., & Machado, C. A. R. (2025). Predicting delays and cost overruns in construction projects using machine learning models. International Journal of Project Management Studies, 7(1), 1–14.

Santiana, I. M. A., Wibawa, I. G. S., Wiraga, I. W., Sujahtra, I. W., Budiadi, I. M., & Yusuf, M. (2026). Determinants of variation orders and their impact on cost overrun in coastal construction projects: A case study in Bali, Indonesia. International Research Journal of Engineering, IT and Scientific Research, 12(2), 14–24.

Santosa, I. G., & Yusuf, M. (2025). Integration of ergonomic principles in the design and construction of car wheel polishing tools to improve operator performance. International Research Journal of Engineering, IT and Scientific Research, 11(4), 105–113.

Sholekah, A. N. (2026). Project acceleration analysis using Precedence Diagram Method and crashing approach in irrigation construction projects. Jurnal Teknik Sipil dan Lingkungan.

Sudiajeng, L., Tarwaka, T., Sutapa, I. K., Sudana, M., & Yusuf, M. (2023). Ergonomic tetrapod reduces the MSDs risk and productivity of steel-bar assembly for reinforcement concrete beams. International research journal of engineering, IT & scientific research, 9(1), 1-13.

Susanti, R. (2020). Cost overrun and time delay of construction project in Indonesia. Journal of Physics: Conference Series, 1444(1), 012050.

Thoengsal, J. (2024). Project acceleration analysis using the crashing method with alternatives for adding manpower and additional working hours in drainage works. Journal of Research in Engineering Science and Technology.

Tofighian, A. A., & Naderi, B. (2015). Modeling and solving the project selection and scheduling. Computers & Industrial Engineering, 83, 30-38. https://doi.org/10.1016/j.cie.2015.01.012

Yusuf, M., Sudiajeng, L., Suryawan, K. A., & Sudana, I. M. (2022). Redesign of Ergonomic Worktables in Reinforced Concrete Sheet Works Reduce Ergonomic Risk Level. In Proceedings of the 5th International Conference on Applied Science and Technology on Engineering Science iCAST-ES, ScitePress Digital Library (pp. 370-374).

Published

2026-05-07

How to Cite

Wibawa, I. G. S., Santiana, I. M. A., Wiraga, I. W., Arya, I. W., Surya Negara, D. R. S., & Yusuf, M. (2026). Time–cost trade-off analysis using the precedence diagram method in residential construction projects: A case study in Bali, Indonesia. International Research Journal of Engineering, IT and Scientific Research, 12(3), 25–35. https://doi.org/10.21744/irjeis.v12n3.2604

Issue

Section

Research Articles