Time and cost trade-offs between overtime and workforce expansion for remaining structural work in a building project in Bali

https://doi.org/10.21744/irjeis.v12n6.2623

Authors

  • I Gede Sastra Wibawa Politeknik Negeri Bali, Badung, Indonesia
  • I Made Anom Santiana Politeknik Negeri Bali, Badung, Indonesia
  • I Nyoman Ramia Politeknik Negeri Bali, Badung, Indonesia
  • I Made Budiadi Politeknik Negeri Bali, Badung, Indonesia
  • I Wayan Sudiasa Politeknik Negeri Bali, Badung, Indonesia
  • M. Yusuf Politeknik Negeri Bali, Badung, Indonesia

Keywords:

construction scheduling, least-cost analysis, overtime, analysis, project crashing, time–cost tradeoff, workforce expansion

Abstract

Schedule acceleration requires comparing additional resource costs with time-dependent overhead savings. This quantitative case study evaluates overtime and workforce expansion for remaining structural work in the XYZ Tabanan building project, Bali, Indonesia. A Microsoft Project precedence network and Microsoft Excel cost calculations compare eight acceleration scenarios with a baseline of 200 working days and IDR 74.414 billion. The Monday–Saturday calendar places the unaccelerated structural completion milestone on 20 October 2026, starting on 2 March 2026 without national-holiday exclusions. Costs comprise IDR 70.000 billion in direct costs, IDR 2.414 billion in allocated fixed indirect costs, and overhead of IDR 10 million per active working day; contractor profit and value-added tax are excluded. In the reported outputs, four hours of overtime yields 114.62 working days and IDR 74.351 billion, while workforce scenario W4 yields 72.98 working days and IDR 74.076 billion. Time reductions are 42.690% and 63.510%, and cost reductions are 0.085% and 0.455%, respectively. Workforce expansion has the lowest reported cost, reflecting overhead savings that exceed its additional direct cost. However, reproducing the accelerated durations requires the activity-level network, calendar settings, and trade-specific resource assignments. The scenario ranking therefore remains conditional on schedule and cost validation.

Downloads

Download data is not yet available.

References

Agarwal, A. K., Chauhan, S. S., Sharma, K., & Sethi, K. C. (2024). Development of time–cost trade-off optimization model for construction projects with MOPSO technique. Asian Journal of Civil Engineering, 25(6), 4529-4539.

Chang, C. K., Hanna, A. S., Lackney, J. A., & Sullivan, K. T. (2007). Quantifying the impact of schedule compression on labor productivity for mechanical and sheet metal contractor. Journal of Construction Engineering and Management, 133(4), 287-296.

De, P., Dunne, E. J., Ghosh, J. B., & Wells, C. E. (1995). The discrete time-cost tradeoff problem revisited. European journal of operational research, 81(2), 225-238. https://doi.org/10.1016/0377-2217(94)00187-H

Demeulemeester, E. L., Herroelen, W. S., & Elmaghraby, S. E. (1996). Optimal procedures for the discrete time/cost trade-off problem in project networks. European journal of operational research, 88(1), 50-68. https://doi.org/10.1016/0377-2217(94)00181-2

El-Rayes, K., & Kandil, A. (2005). Time-cost-quality trade-off analysis for highway construction. Journal of construction Engineering and Management, 131(4), 477-486.

ElSahly, O. M., Ahmed, S., & Abdelfatah, A. (2023). Systematic review of the time-cost optimization models in construction management. Sustainability, 15(6), 5578.

Fardila, D., & Adawyah, N. R. (2021). Optimasi Biaya dan Waktu Proyek Konstruksi dengan Lembur dan Penambahan Tenaga Kerja. Inersia Lnformasi Dan Ekspose Hasil Riset Teknik Sipil Dan Arsitektur, 17(1), 35-46.

Feng, C. W., Liu, L., & Burns, S. A. (1997). Using genetic algorithms to solve construction time-cost trade-off problems. Journal of computing in civil engineering, 11(3), 184-189.

Feng, C. W., Liu, L., & Burns, S. A. (2000). Stochastic construction time-cost trade-off analysis. Journal of computing in civil engineering, 14(2), 117-126.

Hanna, A. S., Chang, C. K., Lackney, J. A., & Sullivan, K. T. (2005b). Overmanning impact on construction labor productivity. In Construction Research Congress 2005: Broadening Perspectives (pp. 1-10).

Hanna, A. S., Taylor, C. S., & Sullivan, K. T. (2005a). Impact of extended overtime on construction labor productivity. Journal of construction engineering and management, 131(6), 734-739.

Hartmann, S., & Briskorn, D. (2022). An updated survey of variants and extensions of the resource-constrained project scheduling problem. European Journal of operational research, 297(1), 1-14. https://doi.org/10.1016/j.ejor.2021.05.004

Hazır, Ö., Erel, E., & Günalay, Y. (2011). Robust optimization models for the discrete time/cost trade-off problem. International Journal of Production Economics, 130(1), 87-95. https://doi.org/10.1016/j.ijpe.2010.11.018

Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European journal of operational research, 165(2), 289-306. https://doi.org/10.1016/j.ejor.2004.04.002

Jeunet, J., & Orm, M. B. (2020). Optimizing temporary work and overtime in the Time Cost Quality Trade-off Problem. European Journal of Operational Research, 284(2), 743-761. https://doi.org/10.1016/j.ejor.2020.01.013

Kelley Jr, J. E. (1961). Critical-path planning and scheduling: Mathematical basis. Operations research, 9(3), 296-320.

Randolph Thomas, H., & Horman, M. J. (2006). Fundamental principles of workforce management. Journal of Construction Engineering and Management, 132(1), 97-104.)

Republic of Indonesia. (2021). Government Regulation No. 35 of 2021 concerning fixed-term employment agreements, outsourcing, working time and rest periods, and termination of employment. https://jdih.kemnaker.go.id/asset/data_puu/PP352021.pdf

Son, P. V. H., & Nguyen Dang, N. T. (2023). Solving large-scale discrete time–cost trade-off problem using hybrid multi-verse optimizer model. Scientific Reports, 13(1), 1987.

Thomas, H. R., & Raynar, K. A. (1997). Scheduled overtime and labor productivity: Quantitative analysis. Journal of construction engineering and management, 123(2), 181-188.

Thomas, H. R., Riley, D. R., & Sinha, S. K. (2006). Fundamental principles for avoiding congested work areas—A case study. Practice Periodical on Structural Design and Construction, 11(4), 197-205.

Tommelein, I. D. (2024). About time-cost trade-offs in takt planning.

Vanhoucke, M., Demeulemeester, E., & Herroelen, W. (2002). Discrete time/cost trade-offs in project scheduling with time-switch constraints. Journal of the Operational Research Society, 53(7), 741-751.

Widiastuti, E., Sugiarti, M. F., Yuliana, C., & Karim, A. (2025). Optimasi Waktu dan Biaya Proyek Gelanggang Olahraga Kalimantan Selatan dengan Metode Time Cost Trade-Off. Jurnal Manajemen Teknologi & Teknik Sipil, 8(1), 79-92.

Woo, S. (2016). Simulation analysis of labor performance during overtime and impact on project duration. KSCE Journal of Civil Engineering, 20(7), 2614-2623.

Published

2026-10-03

How to Cite

Wibawa, I. G. S., Santiana, I. M. A., Ramia, I. N., Budiadi, I. M., Sudiasa, I. W., & Yusuf, M. (2026). Time and cost trade-offs between overtime and workforce expansion for remaining structural work in a building project in Bali. International Research Journal of Engineering, IT and Scientific Research, 12(6), 148–159. https://doi.org/10.21744/irjeis.v12n6.2623